Works Zone 1
- Barriers erected around the works area (23.04.2024)
- Excavate for gully and new kerb line
- Install new gully
- Install Tactile Paving and Kerbs (25.04.2024)
- Pour Remaining section of footpath (29.04.2024)
- Remove barriers around the work area (01.05.2024)
Works Zone 2
- Barriers erected around the work area (22.04.2024)
- The road tar will be cut at the face of the new kerb line
- Excavate for Retaining wall and pour foundation
- Install Tactile Paving and Kerbs (25.04.2024)
- Pour Remaining section of footpath (30.04.2024)
- Remove barriers around the work area (01.05.2024)
Note
- There will be no work vehicles or machinery outside the work zones during construction.
- All works will be done with within the work zone barriers
- There will be one traffic marshal at Vienna woods entrance at times during the working day